We are really pleased with the windows... Despite the snafu on the cut outs for 4 of them, that was quickly resolved, and the OSB team managed to finish the installs today. In addition, they got the french door for the Dining room in as well. They look great, and everyone is impressed with the quality. We opted for standard double-hung windows from the Marvin Integrity line. This is thier 'value line', but are still thermal pop-outs for easy cleaning.
The rough wiring is complete, and the Mason has finished his foundation for the heater. Paul expects to get the rough plumbing done by the end of the week, which means they could start sheetrocking very soon! As a matter of fact, Jeb reviewed a rough schedule with us today, and its aggressive but very doable:
- 7/24- Work on siding
- 7/31- Move inside, hang sheetrock
- 8/7- (Jeb vacation,) have taper work on interior
- 8/14- Lor and I work on interior painting, while OSB does the siding.
- 8/21- install pine floor, sand and finish. Meanwhile, mill the trim.
- 8/28- install interior doors and trim.
- 9/4- install kitchen, work on trim, install countertop.
- 9/11- install finished stairs
- 9/18- Punch out!
Hard to believe, this has all gone by so fast, but the end is really in sight. The exterior trim was delivered yesterday, so Loralee has begun painting it. We have the rest of the week, as they won't need it until next week. In addition, we need to urethane the windows.